Crystal Palace Refurbishment E & P Works
View on Map
Home > Case Studies > Crystal Palace Refurbishment E & P Works
Crystal Palace Station is a Grade II Listed Building and dates from 1854 and is an important element of the East London Line and key to the future redevelopment of Crystal Palace Park for the 2012 Olympics.
A complete refurbishment was required to be carried out comprehensively and sympatheticly in accordance with Heritage listings.
Scope of Works
- Total refurbishment of Relay Room
- Points Heating installed
- D&O Cabinets installed
- Platform and Stair Lighting
- New Switch Rooms
- Buffer Stops Lights installed
Overview
- Contract: Crystal Palace Refurbishment E & P Works
- Principal contractor: Colas Rail
- Engineer: Giffen Group Ltd
- Client: Network Rail
- Type of work: Refurbishment E&P Works
- Contract value: £500,000
- Division: Rail